NYSEG has begun upgrades

After staging equipment by the RRVA entrance yesterday, NYSEG has begun upgrades to our infrastructure.

Equipment staged at entrance to RRVA

From Greg Gomez: They trench, put the conduit in and cover it back up.  The wires will be dragged through later, so they are moving very fast.  More good news: when they cut the road it will be done in halves which will keep the road passable for everyone.  They will trench half the road, put in the conduit and cover it back up, then they will cut the other half of the street.  They expect to complete all trenching and backfilling by the end of next week.

Trench along the side of Pines Dr.